Lacey Court, Lacey Green, Wilmslow, Cheshire SK9 4BH
MAN/00EQ/LIS/2022/0006 · LIS · Cheshire East · decided 3 Feb 2023
The tribunal decided that each garage is the responsibility of its owner, so the costs of major works to the garages cannot be recovered through the service charge.
| Outcome | Not payable |
|---|---|
| Section 20C (landlord's costs of the case) | Not applied for |
| Section 20 consultation | Not in issue |
| Who applied | Landlord or management company |
| Freeholder / landlord | Lacey Court Limited |
| Management company | none named |
| Managing agent | none named |
| Building | A block, 31 flats |
| Service charge years in dispute | not stated |
| Items in dispute | major works |
| Items disallowed or reduced | major works |
| Total demanded | not stated as one figure |
| Total found payable | not stated as one figure |
| Fees or costs ordered | none stated |
Read from the decision automatically: a regular-expression pass, then a language model whose every value must quote the decision word for word. Compare with the original.
What the decision says
- flats n
there are 31 flats in total
- freeholder
The Management Company owns the freehold of Lacey Court
- outcome
the costs of major works to the garages are not payable as part of the service charges
- items reduced
the costs of major works to the garages are not payable as part of the service charges
The passages each figure was read from, verbatim. People's names are replaced with [name].
The original
If this decision relates to your home and you'd like it removed from this site, email hello@rentrisecheck.uk with the address or the case reference (removal requests).
Spotted an error on this page? Email hello@rentrisecheck.uk with what is wrong; the decision's reference goes in the subject.
Past decisions are not a prediction. Each tribunal decides on the evidence in front of it.