Courtlands, 29c Clarence Parade, PO5 2ET
CHI/00MR/LIS/2019/0011 · LIS · Portsmouth · decided 1 Jul 2019
The Tribunal could not decide whether the proposed water pressure works are payable, but construed the lease to mean that the reasonable cost of works to remedy a pipework or pressure problem would be recoverable from all lessees, with a proper report and fresh section 20 consultation needed first.
| Outcome | Other decision |
|---|---|
| Section 20C (landlord's costs of the case) | Not applied for |
| Section 20 consultation | Not in issue |
| Who applied | Landlord or management company |
| Freeholder / landlord | Christie Estates Southern Limited |
| Management company | none named |
| Managing agent | Dack Property Management Limited |
| Building | A block, 10 flats |
| Service charge years in dispute | not stated |
| Items in dispute | repairs and maintenance |
| Items disallowed or reduced | none stated |
| Total demanded | not stated as one figure |
| Total found payable | not stated as one figure |
| Fees or costs ordered | none stated |
Read from the decision automatically: a regular-expression pass, then a language model whose every value must quote the decision word for word. Compare with the original.
What the decision says
- flats n
There are ten flats in all
- agent
Representative : Dack Property Management Limited,
- outcome
The best that the Tribunal can do is to construe the lease
The passages each figure was read from, verbatim. People's names are replaced with [name].
The original
If this decision relates to your home and you'd like it removed from this site, email hello@rentrisecheck.uk with the address or the case reference (removal requests).
Spotted an error on this page? Email hello@rentrisecheck.uk with what is wrong; the decision's reference goes in the subject.
Past decisions are not a prediction. Each tribunal decides on the evidence in front of it.