Centre Point House, 15A St Giles High Street, London WC2H 8LW
LON/00AG/LSC/2023/0012 · service charges · Camden · decided 25 Mar 2024
The tribunal decided in principle that the costs of the proposed façade works and project manager would be recoverable from leaseholders whose leases are not qualifying leases, but not from the leaseholders of listed flats with qualifying leases under the Building Safety Act 2022.
| Outcome | Other decision |
|---|---|
| Section 20C (landlord's costs of the case) | Not clear |
| Section 20 consultation | Not in issue |
| Who applied | Landlord or management company |
| Freeholder / landlord | Yen Huang (Flat 15) (11) Ginger Global (UK) 2021 Ltd |
| Management company | none named |
| Managing agent | none named |
| Building | A block, 36 flats |
| Service charge years in dispute | not stated |
| Items in dispute | major works, other |
| Items disallowed or reduced | none stated |
| Total demanded | £6,762,860 |
| Total found payable | not stated as one figure |
| Fees or costs ordered | none stated |
Read from the decision automatically: a regular-expression pass, then a language model whose every value must quote the decision word for word. Compare with the original.
What the decision says
- flats n
Within the six residential storeys are situated 36 duplex flats
- outcome
If costs were incurred for the QLTA for a project manager to supervise
- total demanded
to date approximately £6,762,860 has been demanded from leaseholders
The passages each figure was read from, verbatim. People's names are replaced with [name].
The original
If this decision relates to your home and you'd like it removed from this site, email hello@rentrisecheck.uk with the address or the case reference (removal requests).
Spotted an error on this page? Email hello@rentrisecheck.uk with what is wrong; the decision's reference goes in the subject.
Past decisions are not a prediction. Each tribunal decides on the evidence in front of it.