35 Allen Close, Wheathampstead, St Albans, AL4 8TH
CAM/26UG/LSC/2024/0031 · service charges · St Albans · decided 6 Jul 2025
The tribunal found the major works charges for the roof and windows payable in full, as the works fell within the landlord's repairing obligations and were reasonably incurred.
| Outcome | Payable as demanded |
|---|---|
| Section 20C (landlord's costs of the case) | Not applied for |
| Section 20 consultation | Not in issue |
| Who applied | Leaseholder(s) |
| Freeholder / landlord | St Albans City and District Council |
| Management company | none named |
| Managing agent | none named |
| Building | A block, 8 flats |
| Service charge years in dispute | 2023 |
| Items in dispute | major works |
| Items disallowed or reduced | none stated |
| Total demanded | £12,285.02 |
| Total found payable | not stated as one figure |
| Fees or costs ordered | none stated |
Read from the decision automatically: a regular-expression pass, then a language model whose every value must quote the decision word for word. Compare with the original.
What the decision says
- flats n
that building consists of eight flats four of which are let on long leases
- years
1 April 2023 – 31 March 2024 and 1 April 2023 and 31 March 2024
- outcome
The Tribunal determines the sums demanded payable in full.
- total demanded
major works in the sum of £12,285.02.
The passages each figure was read from, verbatim. People's names are replaced with [name].
The original
If this decision relates to your home and you'd like it removed from this site, email hello@rentrisecheck.uk with the address or the case reference (removal requests).
Spotted an error on this page? Email hello@rentrisecheck.uk with what is wrong; the decision's reference goes in the subject.
Past decisions are not a prediction. Each tribunal decides on the evidence in front of it.